PowerChute Network Shutdown v4.x fails to shutdown the vCenter Server VM or ESXi hosts when using a local account.
Issue: PowerChute Network Shutdown v4.x fails to shutdown the vCenter Server VM or ESXi hosts when using a local account. This issue manifests itself...
User note for FM units, when reconfiguring a primary unit to an expansion unit
Issue: FM Reconfiguring a Primary unit to a expansion unit   Product line: FM   Environment: Data Center Cooling   Cause:   Resolution: Remedy: Before...
How do I go about Resetting or Reconfiguring my DG5 board.
Issue: DG5 Configuring the unit type   Product line: DG5   Environment: Data Center Cooling   Cause:   Resolution: 1. Path: Blank Button >> enter...
How long are the intake and exhaust hoses on the ACPA4000?
Issue: The Length of the intake and exhaust ducts on the ACPA4000   Product line: ACPA4000   Environment: Data Center Cooling   Cause:   Resolution:...
Oil Type for Different Types of Refrigerant
Issue: Oil Type for Different Types of Refrigerant Product line: All AC DX Units Environment: All versions/serials Cause: Oil Maintanence Resolution:...
What is the maximum mounting depth of a 1070mm (42") deep NetShelter SX cabinet with no accessory mounting rails?
Issue: A customer needs to know the maximum available mounting depth.  Product Line: NetShelter SX 1070mm Deep Environment: All versions and serial...
What is the torque specification for the bolts that attach the bolt-down bracket to the NetShelter cabinet?
Issue: A customer wants to make sure they have the correct torque for the bolts that attach a bolt-down bracket to the NetShelter cabinet.   Product...
Can the vertical cable trough from the rear of the front left hand rail of a NetShelter Networking cabinet be moved to the left hand side, or is there a version that installs onto the right hand rail?
Issue:  A customer is asking if the vertical cable trough can be moved to the right hand rail, or if a version for the right hand rail is available.  ...
What are the features of the switched outlet groups on my SMT, SMX, or SRT Smart-UPS?
Issue: Next Generation Smart-UPS have switchable outlet groups which can be used to reboot hung equipment, sequence the bootup/shutdown process, or...
Which steps should I take for installing and configuring my NEW APC Back-UPS?
Issue: Which steps should I take for installing and configuring my NEW APC Back-UPS? Product Line: All APC Back-UPS product families. Environment:...