APC will provide guidance as to how to physically connect the 3-Phase UPS to the mains. The actual electrical connection will be accomplished by a customer designated electrician or an APC referred electrical contractor. In either case, APC Authorized Personnel will be on-site to oversee the installation of the product.
APC will:
- Meet with customer to understand UPS environment requirements
- Evaluate accessibility for delivery of UPS:
Sizing requirement for entryways/hallways
Suitable delivery path
Acceptable floor loading (rolling)
- Evaluate suitability of UPS environment:
Air conditioning consumption
Pacing requirements
UPS electrical configuration
Acceptable floor loading (rolling)
- Meet with installing electrician to review electrical installation requirements
|
|
Benefits to Customer:
- Customer resources freed to concentrate on core business focuses
- Assurance of proper installation
- Ease of installation
Important Points:
- Customer designated electrician or an APC referred electrical contractor will accomplish the actual electrical connections
- Customer supplies electrical equipment up to the connection point of the UPS
- Customer may choose in-house electricians, their own contractor or and APC designated contractor
- Allow for a two week lead time in scheduling
- APC is not responsible for wiring before and after UPS
- APC will be present during the installation
- Service is part of Premium and Enterprise Power Reliability programs
- Part Number: WICS
|
|